Power Plant Standards
The Electric and Safety Reliability Branch (ESRB) helps maintain reliable electric generation for the public by ensuring power plants comply with GO 167-B Maintenance, Operation, and Logbook Standards. GO 167-B specifies who must file compliance documents according to plant type and capacity. Unless exempt by GO 167-B, Generating Asset Owners (GAO) are required to file the following documents with the Safety and Enforcement Division.
- Maintenance Standards Filing Requirements
- Maintenance Plan Summary - Due February 1, 2025
- Certification with Maintenance Standards - Due February 1, 2025
- Operation Standards Filing Requirements
- Operation Plan Summary - Due February 1, 2024
- Certification with Operation Standards - Due February 1, 2024
- Logbook Standards Filing Requirements
- Thermal Logbook Verified Statement - Due February 1, 2025
- Hydroelectric Logbook Verified Statement - Due February 1, 2025
The following table shows who must file compliance documents. For a more detailed table, download Required Filings Under GO 167-B and Other Required Duties.
FACILITY TYPE |
CAPACITY |
MAINTENANCE SUMMARY PLAN |
MAINTENANCE CERTIFICATION |
OPERATION SUMMARY PLAN |
OPERATION CERTIFICATION |
LOGBOOK VERIFICATION |
Any type under 50 MW |
< 50 MW |
Exempt |
Exempt |
Exempt |
Exempt |
Exempt |
Thermal (Fossil Fuel) |
> 50 MW |
Yes |
Yes |
Yes |
Yes |
Yes |
Geothermal |
> 50 MW |
Yes |
Yes |
Yes |
Yes |
Yes |
Hydroelectric |
> 50 MW* |
Yes** |
Yes** |
Yes** |
Yes** |
Yes |
Wind |
> 50 MW |
Yes |
Yes |
Yes |
Yes |
Exempt |
Solar |
> 50 MW |
Yes |
Yes |
Yes |
Yes |
Yes*** |
New or Acquired Plant |
> 50 MW |
Yes |
Yes |
Yes |
Yes |
Yes |
- * includes switching centers controlling > 50 MW
- **unless licensed by FERC
- *** for solar thermal only (photovoltaic is exempt)
If you have additional questions, please visit our Frequently Asked Questions (FAQ) page or contact us.
Other Filings
- Nuclear Generating Facility - Please send all filings required under GO 167-B to nuclearfilings@cpuc.ca.gov
The Commission has authority over the operation and safety of all non-nuclear facilities at and associated with Diablo Canyon Power Plant. The U.S. Nuclear Regulatory Commission (NRC) has exclusive authority over nuclear safety.
- Change in Long-Term Unit Status or Plant Ownership
- Safety-Related Incident
- Daily Status Report
- NERC GADS